Specialist Roof Sheeting & Cladding Advisory Service
Established since 2001

Technical & Training Service Ltd aims to:

• provide a comprehensive roof & wall cladding survey and condition report service to the owners and occupiers of existing industrial and commercial premises.

• provide training and qualifications for the people that install roof & wall cladding systems, as well as their designers, supervisors and managers.

Home
About us
Consultancy
Training
Auto CAD Design
Portfolio
Published articles
Contact

An article by Mike Long (FloR AIIRSM, Eng Tech, Tech Weld I)
Published in RCI (Roofing Cladding & Insulation) May 2005

article

What else can go wrong?
Joe Bloggs Ltd was formed by Joe after he came off the tools 20 years ago. He decided he could earn more money by working for himself, rather than line the pockets of his employers.
Joe had no formal training, but had been around a while and knew the ropes - or so he thought. His company grew from being a one-man band to an employer of 30 men on site and eight people in the office. Turnover had increased and he was making a steady living, working on fairly simple big sheds clad in profiled metal, as well as repairs.

Taking a bigger slice
The industry had grown in complexity - particularly the profiled sheet market - and the demand for more complicated systems and

demand for more complicated systems and details had increased. Drawings and design input were standard requirements for most jobs, and better workmanship and improved supervision were demanded by Building Regulations and new high-tech roofs. Joe realised that if he was to continue he would need to take a slice of this market, because there were fewer simple big sheds to clad. There shouldn't be a problem, he thought, one system is much the same as another. He didn't have a drawing office as such, but his mate's son had just finished a CAD course at college - he would soon pick up the finer points of the business. Joe did most of the estimating, so there was no problem there. His two supervisors had been with him from the start, having also worked on the tools, and were capable of running the jobs he had being doing. So Joe dipped his toe into the market sensibly by carrying out a few small low-key projects, which went pretty well. Seeing the benefit, he sought bigger and more lucrative jobs.

Hitting the big time

Eventually Joe won a large contract for a sports hall and swimming pool with high specification acoustic lining, aluminium bull noses, curved sheets etc. The main contractor was new to him but it seemed ok, although he did have to drop 5% to get the job. The specification was complex but Joe was fairly confident that he had picked up everything. The contract documents were not standard - a bit weighty - but the friendly surveyor assured him, so Joe signed and returned them. Joe went along to the pre-start meeting to arrange for scaffolding and access arrangements with the site manager, who informed him that they were laying drains down one side of the building, and there were power cables crossing the roof at one end. Joe had assumed, but not confirmed, that free access would be available all around the building. That meant that specialist scaffolding and huge crane had to be provided by Joe, which he had not allowed for in his quotation. Furthermore, the job would take much longer than had been allowed for, so labour cost would also be higher. Joe could see no options other than to talk to his friendly surveyor to hopefully agree for extra time and payment. However the surveyor he had been dealing with had moved on, and his replacement was adamant that the terms of the contract would apply and that there was no extra money or time. Joe had little option that to bite the bullet and accept this. After all he did have a reasonable margin built in, and he could, with a little luck, absorb these costs.
The job was due to start in May and finish in September. Joe's new draughtsman was working on the drawing, and materials were ordered accordingly. However, the special colours required by the project could not be made until June, as bulk orders had not been placed in sufficient time - Joe had not previously checked with the manufacturer. At this point Joe was having kittens as he could see the liquidated and ascertained damaged (LAD) of £25k/week looming. After much anguish and begging (not to mention the offer of a financial incentive) he managed to persuade an alternative manufacturer to deliver the materials when required - only to learn a week before delivery that the start date had been delayed by three months, due to a problem with the steelwork design.

Pages 1 | 2 | 3 next>>

Copyright © 2007 Technical and Training Services